1. House has been staked out, ready for excavation to begin
2. Excavation begins for the crawl space foundation
3. Crawlspace excavated, ready for the foundation (1)
4. Beautiful view of Squaw Butte Mountain in the background
5. Foundation footings poured and concrete blankets cover to keep footings from freezing
6. Foundation Stemwalls being formed. Rebar installed as the forms go up. These are 3' tall stemwalls
7. Both foundation footings and stemwalls poured with a concrete pumper
8. Foundation Walls being poured
9. Foundation complete. Excavator digging power trench prior to prepping for sidewalks
10. Front Porch ready for fill. This will be compacted for the front porch concrete. Notice the load bearing concrete columns for the front porch post
11. Rear Patio will also be filled and compacted for concrete patio
12. Transformer and Temporary power pole installed and ready to go
13. Temperatures in the teens and twenty's have held up pouring the concrete slabs. Concrete blankets keep the prep. material from freezing
14. How would you like to see this view in the morning
15. All the concrete work is done.
16. Excavated 100' x 100' parking area. Filled and compacted Pitrun material
17. Trucks arrive the day before set day
18. Exterior walls arrive
19. Trusses and roof sheeting and bunks of intrior walls
19B 3 Semis of walls and trusses arrive
20. Subfloor has been installed the day before. (Subfloor is not a part of the IPH package.) 1st of 3 bunks of interior walls
21. 1st exterior wall moves into place
22. Exterior walls have Milgard Tuscany Vinyl Frame windows pre-installed.
23. 1st of 3 bunks of interior walls, set in Living room with one set in the Master Bedroom.
23B 2nd of 3 bunks of Interiors
24. Framer has a panel plan ahead of time to layout on the subfrloor where all walls go. Yes they are numbered.
25. Garage Wall
25B. 1 of two Garage walls being set in place
26. This house is all 9 foot tall walls thoughout
27. Interior walls have the double top plates pre-installed.
28. Exterior Wall
29. Front Door Wall
30. All Exterior walls in place in 2 hrs.
31. Front elevation. You can see all the interior walls inside ready to be set.
32. Trusses offload on the ground
32A. All exterior and interiors walls set in 5 hrs. Trusses offloaded to be set on day 3
Day 2 - All post and Glu-Lam beams installed.
34 Rear Patio. The two windows in this wall were special ordered and will be field installed
35. Day 3 from when the walls are set. All trusses are in place.This custom home has 2,556 SF of heated area
36. Trusses cover the rear patio. Notice small scrap pile of wood. Rear Patio is 609 SF
37. All trusses in place, front elevation.451 SF of covered front porch
38. 4 days from when the house arrived, all the roof sheeing is in place
39. West Side
40. Garage Side
41 Rear Elevation
42. Day 5 Roof is dried in
43. 8 days from when the house arrived, all framing is done. Subcontractors begin. This is a Catherdral ceiling
44. Day 10, Plumbing and Electrical are going in. This house has a 1,132 SF garage
45 Framing for zero clearance gas fireplace
47. Sheetrock complete
48. Garage Sheetrock complete_1
50. Appliances Installed, electrical complete
51. Painting the interior doors in the garage
53. Kitchen Cabinets Installed
54. Quartz Solid Surfaces Installed
55. Kitchen Quartz Surfaces Installed
57. Looking into the Master Bath, Mirrors and Light Fixturs installed
58. Custom Mantal and stonework complete
59. Front Elevation
60. Rear an Master Bedroom Elevation
61. Garage Elevation