OUR EXTERIOR WALLS

  • Dry 2×6 16″ on-center 8 ft. (Optional 9 ft. original walls) 1 or 2 stories. Basements, elevated entries and 2-story great rooms, closets – not a problem.

  • We use a 3.5″ x 9″ glue-lam beam for all exterior door and window headers.  Roof snow load will change header sizes.

    Our exterior walls are completely sub-sheeted and nailed with 8d galvanized screw nails (not staples).

  • Our Milgard windows (New Tuscany Vinyl Frame, SuperMax Low E, Limited Lifetime Factory Window Seal Failure and Breakage Warranty) are pre-installed in your walls. (www.milgard.com)

  • We install Tyvek building wrap which serves as an air infiltration barrier and a protection for your insulation.

  • Pre-Primed Louisiana-Pacific SmartSide Siding is then installed. We can send sub-sheeted walls when you will be applying a field-installed siding (i.e. Stucco, Stone, Hardie Siding, Vinyl Steel, Cedar, etc.).

  • 1×4 Primed Window Trim is installed around your windows.

  • Therma-Tru Exterior Insulated Smooth Star Doors are pre-installed in the Exterior Panels (Option: We have the full line of Therma-Tru Doors available). (www.thermatru.com) All door locksets are by owner. Note: Garage Roll-Up Doors are not included. These are installed by a Sub-Contractor.

 

 

OUR INTERIOR WALLS

  • Our Interior Walls are Pre-Built and Double-Plated Dry 2×4, 16″ on-center according to your plan.
  • We provide Sheet Rock Backing.
  • 2×6, 16″ on-center interior plumbing walls per plan.

ABOUT OUR ROOFS

  • Factory Made Engineered Roof Trusses are included. (Snow load? No problem. Let us know what it is.)
  • Gable Trusses are sub-sheeted.
  • Our Trusses are engineered to the standards of Mitek.
  • We can design and build the trusses you need for your home (i.e. Flat Commons, Vaults, Scissors).
  • Roof Sheeting and all materials for your boxed soffits are included.
  • When 2 story or working over a basement or concrete, we use our optional 4×2 wood floor trusses, web framing to allow plumbing, HVAC, electrical. These take the place of the “I” Joist.