1. Foundation is poured
2. Foundation and concrete slabs are in
3. Crawl Space joist and subfloor is installed prior to the IPH package arriving
4. IPH 1st Floor Framing package arrives
5. 1st Floor also includes pre-fabricated stairs to 2nd story
5A 1st off are the bunk of interior walls
6. Crane is ready to begin setting 1st story walls
7. Pre-built stairs are temorarily set in the garage
8. 2x6 Walls being set with Milgard Tuscany windows pre-installed
9 Elevated Front Entry Walls
10 Garage wall with Glu-Lam headers
11. Last exterior wall. 2 hrs from the set of the 1st wall. House wrap pre-installed
12. 5.5x28.5 Glu-Lam beam being crane set. This will support the 2nd story. Roof has 100 lbs per SF snow load requirement
13. Beams being completed
14. End of day 1. All 2x6 exterior and 2x4 interior walls for the 1st floor are installed
15. 16 inch floor trusses and inch and one eight thick subfloor are set for 2nd story on day 2
16. Floor trusses over the kitchen
17. Day 3. Second story walls arrive
18. 2nd story walls set in place
19 Another 2nd story wall is lifted to be set in place
20. 2nd story wall
21. All 2nd story walls are in place
22. Still day 3. Trusses arrive and are bunk lifted and ground set
23. 250 lb cast iron tub set in 2nd story bath
24. End of day 3. trusses set in place (1)
25. Day 4 Sub-Fascia and roof sheeting begin
26. Living room vaulted ceiling on top of 9ft 2x6 walls
27. Pre-built stairs are in place
28. End of day 5. All, except elevated entry trusses, are in place and roof sheeting being nailed in place
29. 4 weeks after the IPH package was set. Ice and Water Shield Installed on the roof. Rough plumbing complete, Electrical started (1)
30. 4 weeks from when the IPH Package House arrived and set. Siding delivered. Roof shingles loaded on the roof for roofer
31. Interior-great Room Framing (1)
32. Trenching for underground utilities
32B. Conditioned Crawl Space Stemwalls Foamed
33. Siding going on
34. Siding done. Ready for stonework and paint
35. Painted. Finishing up stonework. Asphalt driveway installed
36. Rear of house (1)
37. Rear of House
38. Front Gables
39. Great Room, sheetrocked and painted
40. Cabinets going in. Electrical Trim progressing. Approx 90 days from when the house was set. Customer doing interior finish work
41. Master Bath Vanity area
42. Customer installed stonework completed. Exterior complete, ready for winter (1)
43. Cabinet work continues (1)
44. Tile Master Shower (1)
45. Tile Master Shower (2
46. Solid Surfaces Arrive
47. Master Bath Solid Surfaces in
48. Master Bath
49. Kitchen Solid Surfaces installed (3)
50. Kitchen Solid Surfaces installed (4)
51. Kitchen Solid Surfaces installed (1)
52. Kitchen Solid Surfaces installed (2)
53. Customer did his own trim carpentry over the fireplace.
54. Customer did his own tile work. Kitchen backsplash being done
Hailey, ID - Front Entrance View
56. Landsscaping (3)
Haliey, ID - Landscaped
58. Customer built Gate
Hailey, ID - This is the 2nd home built for this couple