2. Foundation excavated. These foundation walls will be 42 inches tall over 8 x 16 inch footings
3. Foundation contractor moves in to layout house footprint to get ready for footing forms
4. Foundation poured and garage slab in place
5. This has a condition crawl space
6. Ready for interior pony wall, floor joist and subfloor
7.The subfloor materials arrive. They are not a part of the IPH Framing Package. They are installed before the package arrives
8. Crawl Space Floor Joist installed. Ready for subfloor. Garage slab poured
9. Subfloor installed. What a View
10. Ready for the IPH house to arrive on set day
11. Trusses staged to set after the walls go up
12. First Truck of walls
13. Brought the 75' long trucks-trailers accross a field to the building site
14. 1st wall
15. 1st wall crane set in place. Walls have Milgard Tuscany windows pre-installed
16. 1st wall going into place (1)
17. Walls continue.
18. Garage door wall.
19. Walls going in. We use Glu-Lam Beams for all exterior door and window headers
20. We use a minimum of a 20 ton crane to lift and set walls
21. Front porch footings ready to pour. Background garage doors. Notice the continous garage door Glu-Lam beam header. Garage is 2x6 studs 16 inches o.c
22 Exterior walls continue. 2x4 temporary braces installed until interior walls set
23. 2x6 Exterior wals, 16 inches o.c. with Milgard Tuscany windows pre-installed along with building wrap
24. The entry has 3 seperate walls with the center pre-framed extended height at 16 ft with the dormer window above (1)
25LAST~1
26. 2nd Truck with Interior walls. Notice the Pre-Built stairs for the 714 SF Bonus Room loaded ontop
27. Pre-Built interior walls craned up and set in the Great Room as a bunk of walls
28.. Interior walls staged in the Great room
29. All the 9ft tall walls are in place. All siding is by owner and field installed
30. All the 9 ft tall exterior and interior walls were installed in 8 hrs. Ready for roof trusses
31. All the roof trusses were installed in 6 hrs. This roof snow (live) load was rated at 70 lbs per SF
32. The Bonus Room Trusses going in. Notice the pre-built stairs are in place
35. Roofing continues as the snow comes off (1)
34. Snow has arrived. These trusses are rated for 70 lbs per SF snow load
33. Stairs in place ready to finish
36. Roofing continues as the snow comes off (2)
37. Siding Front Elevation
44. 714 SF Bonus Room
Blanchard, ID - Front and Side View
39. Siding Rear Elevation. Fireplace chase and fireplace piping installed
40. Garage Side Siding complete
Blanchard, ID - End and Back View with Bonus Room above